Promenadebrug is getting shape, Nijmegen (NL)

05.09.2014

The first part of concrete deck of Promenadebrug was successfully cast on Wednesday 27 August 2014 in Nijmegen (NL).

700m³ of the concrete was poured in order to construct the first 96 m of total 220m long bridge. Next two weeks 60 % of the post-tensioning will be applied. After that the formwork will be removed and reused for the next phases. The remaining 124m will be cast in 2 phases.